The Department of Energy selected 31 SPARK reconductoring and grid enhancing technology projects on September 24, 2026, committing about $1.9 billion that startups can reach through utility recipients. Total project value reaches $5.25 billion because recipients contribute $3.35 billion, about 64 percent of the total. The projects will reconductor or rebuild more than 1,500 miles of line and apply grid enhancing technologies across nearly 21,000 miles, a ratio of about 14 to 1, for a stated gain of more than 23 GW.

Money per mile explains where startup contracts will land. The Entergy project covers about 1,125 miles at a total value of $27.4 million, roughly $24,000 per mile. The PPL Montour rebuild covers 29.3 miles at $142.9 million, roughly $4.9 million per mile. Sensing, line rating software, and power flow hardware cover far more wire per dollar than conductor does, so the larger number of vendor contracts goes to the cheaper technologies, while conductor makers win fewer and larger orders.

Startups hold almost none of the awards. Utilities, cooperatives, and state agencies hold them, with two recipients outside that group: the startup Pitch Aeronautics at $37.0 million federal and the Electric Power Research Institute at $20.9 million. Selection is an intention to fund. Agreements are expected between October 2026 and January 2027, project periods run up to 48 months, and the notice sets minimum capacity gains of 50 percent for physical upgrades and 25 percent for operational technologies. Startups should position now around measured, contractable capacity gains and the technology readiness levels the notice requires, because utility purchasing follows the signed agreements.

Detailed Findings

What Did the Department of Energy Select Under SPARK?

DOE selected 31 projects in 26 states on September 24, 2026, funded from the Grid Resilience and Innovation Partnerships program that the 2021 infrastructure law authorized at up to $10.5 billion over five years. The money is reallocated program funding. DOE describes the selections as intentions to fund, and the figures stay preliminary until agreements are signed. The notice of funding opportunity, number 0003580, issued on March 12, 2026, with applications due May 20, 2026. DOE’s program page lists different dates, February 25 and May 5; the notice document itself controls here.

The 31 divide into four small utility projects, five large utility projects, 18 smart grid projects, and four cross regional projects. Summing the federal shares in DOE’s list gives $1,893 million, which matches the $1.9 billion headline: $476.4 million in the grid resilience topic area, $606.5 million in the smart grid topic area, and $810.4 million in the grid innovation topic area. Total project value sums to $5,252 million. The four cross regional awards, to Colorado, Oklahoma, Ohio, and Indiana, take 43 percent of the federal dollars. DOE describes one of them, the Three Corners Connector between the Southwest Power Pool and the Western Interconnection, as a new high capacity transmission link, which places it outside the reconductoring work.

Which Technologies Appear in the 31 Project Descriptions?

Line rating technology appears in more project descriptions than any other single technology. Eleven of the 31 descriptions name dynamic line rating or a line rating or capacity rating system: Kit Carson Electric Cooperative, Rocky Mountain Power, the Tennessee Valley Authority, American Electric Power, Entergy, Eversource, New England Power, NorthWestern Energy, Orlando Utilities Commission, Pitch Aeronautics, and Public Service Company of New Mexico.

Four descriptions name power flow control or stabilization hardware. NorthWestern Energy pairs advanced power flow control with dynamic line rating on a Montana and Wyoming transfer path, at $26.5 million federal on $53.0 million total. CenterPoint Energy Houston Electric lists an advanced transmission system stabilization device at $50.0 million federal. Duquesne Light lists stabilization devices at $22.2 million federal. The New York Power Authority lists a static synchronous compensator at the Marcy site, $50.0 million federal on $270.0 million total. Together the four draw $148.7 million in federal funds.

Reconductoring appears by name in a smaller group. Arizona Electric Power Cooperative, Kit Carson, PPL Electric, Orlando Utilities Commission (high temperature low sag conductor), Pitch Aeronautics (targeted wire upgrades for Ameren Missouri, Ameren Illinois, and Farmington Electric Utility System), 1803 Electric Cooperative (wire replacement), and Indiana (reconductoring across the PJM and MISO seam) each carry conductor work. Several other projects list transmission line upgrades without stating a conductor type.

Sensing and analytics appear throughout. Kit Carson pairs line rating with advanced sensors and data analytics. New England Power lists targeted field sensors and automated operations software. Powder River Energy lists real time sensors and AI models for planning and predictive maintenance. Guam Power Authority lists AI enabled operational tools. The Orlando project lists AI tools that reduce the number of sensors required, which states a design goal of fewer physical sensors per mile through modeling.

What Does the 14 to 1 Mile Ratio Mean for Vendors?

The ratio means grid enhancing technology vendors will see more contracts and conductor vendors will see larger ones. DOE’s totals give nearly 21,000 miles of grid enhancing technologies against more than 1,500 miles reconductored or rebuilt; some of the enhanced miles may overlap rebuilt lines, and DOE has not published the overlap. The two examples with public detail show the spread in cost. The Entergy project covers about 1,125 miles of existing line for $27.4 million total, about $24,000 per mile, with dynamic line rating, targeted surveys, substation and terminal